9709/42

Mathematics 9709/42February/March 2022

Cambridge AS Level · Mechanics · worked solutions for every part, with the mark scheme

7
questions
50
marks
75
minutes

Topics Energy, Work and Power · Kinematics of Motion in a Straight Line · Forces and Equilibrium · Newton's Laws of Motion · Momentum

Q1Energy, Work and PowerFree sample

A crane is used to raise a block of mass 600 kg600\text{ kg} vertically upwards at a constant speed through a height of 15 m15\text{ m}. There is a resistance to the motion of the block, which the crane does 10000 J10\,000\text{ J} of work to overcome.

(a)

Find the total work done by the crane.

2M
DifficultyMedium-Easy
Worked solution

Approach

Since the block is raised at constant speed, its kinetic energy does not change. The work done by the crane therefore equals the gain in gravitational potential energy plus the work done against the resistance.

Working

The gain in gravitational potential energy is

600×10×15=90000 J600 \times 10 \times 15 = 90\,000\ \text{J}

The work done against the resistance is given as 10000 J10\,000\ \text{J}. Hence the total work done by the crane is

90000+10000=100000 J90\,000 + 10\,000 = 100\,000\ \text{J}

Answer

100000 J100\,000\ \text{J}
Final answer

100000 J

Detailed explanation

Walkthrough

Start by recognizing that the block moves at constant speed vertically. Constant speed means zero acceleration, so there is no change in kinetic energy; all the work done by the crane goes into raising the block's potential energy and overcoming the resistance.

First calculate the gain in gravitational potential energy using ΔEp=mgh\Delta E_{p} = mgh. With m=600kgm = 600\,\text{kg}, g=10m s2g = 10\,\text{m s}^{-2} and h=15mh = 15\,\text{m}, this gives 90000 J90\,000\ \text{J}.

The resistance does not store energy: the crane must supply 10000 J10\,000\ \text{J} purely to overcome it. Therefore the total work done by the crane is the sum of these two amounts, 90000+10000=100000 J90\,000 + 10\,000 = 100\,000\ \text{J}.

Key Takeaways

This question combines gravitational potential energy with work done against a resistance. When an object moves at constant speed, the net work done on it is zero, so the work done by the driving force must balance both the gravitational work and any resistive work.

Common Mistakes

  • Forgetting to add the 10000 J10\,000\ \text{J} of work done against the resistance.
  • Using the mass times height without multiplying by gg.
  • Assuming there is a change in kinetic energy when the speed is constant.

Things to Be Careful About

  • Use a consistent value of gg; the mark scheme here uses g=10m s2g = 10\,\text{m s}^{-2}, giving 600×10×15=90000600 \times 10 \times 15 = 90\,000.
  • The work against resistance is given in joules, so no conversion is needed before adding.
  • The result is a scalar quantity measured in joules.
Techniques used
calculate gravitational potential energy gainedapply work-energy principle at constant speedadd work done against resistance
(b)

Given that the average power exerted by the crane is 12.5 kW12.5\text{ kW}, find the total time for which the block is in motion.

2M
DifficultyMedium-Easy
Worked solution

Approach

Use the relationship that the average power is the total work done divided by the time taken, i.e. P=WtP = \frac{W}{t}, so W=PtW = Pt. Substitute the total work done from part (a) and the power in watts, then solve for tt.

Working

Convert the average power to watts:

P=12.5 kW=12500 WP = 12.5\ \text{kW} = 12\,500\ \text{W}

Use work done=power×time\text{work done} = \text{power} \times \text{time}:

100000=12500t100\,000 = 12\,500 \, t

Solve for tt:

t=10000012500=8 st = \frac{100\,000}{12\,500} = 8\ \text{s}

Answer

8 s8\ \text{s}
Final answer

8 s

Detailed explanation

Walkthrough

The average power exerted by the crane is 12.5kW12.5\,\text{kW}. Power is the rate at which work is done, so P=WtP = \frac{W}{t}, equivalently W=PtW = Pt.

Before substituting, convert the power into watts because the work done in part (a) is measured in joules and time will be in seconds: 12.5kW=12500W12.5\,\text{kW} = 12\,500\,\text{W}.

Using the total work done by the crane from part (a), W=100000JW = 100\,000\,\text{J}, the equation becomes 100000=12500t100\,000 = 12\,500\, t. Dividing both sides by 1250012\,500 gives t=8t = 8 seconds.

Key Takeaways

Power is work done per unit time. This question shows how to rearrange P=WtP = \frac{W}{t} to find time once total work and average power are known.

Common Mistakes

  • Forgetting to convert 12.5kW12.5\,\text{kW} into 12500W12\,500\,\text{W}.
  • Using the potential energy gain 90000J90\,000\,\text{J} instead of the total work done 100000J100\,000\,\text{J}.
  • Reversing the fraction, e.g. calculating 12500100000\frac{12\,500}{100\,000}.

Things to Be Careful About

  • The mark scheme follows on from the candidate's total work done in part (a); here that is 100000J100\,000\,\text{J}.
  • Units must be consistent: joules, watts and seconds.
  • The final time must be stated with seconds.
Techniques used
convert average power to wattsapply work equals power times timesolve for time

The rest of this paper

6 more questions
  • Q2Kinematics of Motion in a Straight Line5M
  • Q3Energy, Work and Power · Forces and Equilibrium · Newton's Laws of Motion5M
  • Q4Energy, Work and Power · Newton's Laws of Motion6M
  • Q5Forces and Equilibrium7M
  • Q6Kinematics of Motion in a Straight Line11M
  • Q7Forces and Equilibrium · Kinematics of Motion in a Straight Line · Newton's Laws of Motion · Momentum12M
Loading the full paper…