9708/12

Economics 9708/12May/June 2015

Cambridge AS Level · AS Level Multiple Choice · answer key with instant marking and worked solutions

30
questions
30
marks
60
minutes

Topics Demand and Supply · Elasticities of Demand · (Legacy) - Externalities and Cost-Benefit Analysis · Exchange Rates · Scarcity, Choice and Opportunity Cost · Factors of Production · +13 more

Tap an option under each question to check it — your score builds as you go.

Q11MScarcity, Choice and Opportunity CostFree sample

In 2013, there was much criticism of a government project to build a new high-speed rail link between two cities.

What is the most likely reason for abandoning such a project?

Options

A   The construction cost is greater than the running cost.
B   The external cost is greater than the external benefit.
C   The future costs are difficult to calculate.
D   The opportunity cost is too high.

DifficultyEasy
Worked solution

Answer

The most likely reason is that the opportunity cost is too high (D). Opportunity cost is the next best alternative forgone. If the resources could produce greater benefits elsewhere, the project should be abandoned. The other options are less fundamental.

Final answer

D

Detailed explanation

Background Concept

Opportunity cost is a fundamental concept in economics. It refers to the value of the next best alternative that must be forgone when a choice is made. Because resources are scarce, every decision involves a trade-off. For a government project, the opportunity cost includes all the other public goods and services that could have been provided with the same resources. If the opportunity cost is too high, meaning the forgone alternatives are more valuable, then the project is not worthwhile.

Understanding the Question

The question asks for the most likely reason to abandon a government project to build a high-speed rail link. It is a multiple-choice question testing the understanding of opportunity cost. The options present different cost concepts: construction cost vs running cost (A), external cost vs external benefit (B), difficulty in calculating future costs (C), and opportunity cost (D). The correct answer is D because opportunity cost is the overarching concept that captures the sacrifice of alternatives, which is the core reason for abandoning a project when resources are scarce.

Approach

To answer this question, we need to evaluate each option in terms of economic reasoning. The most fundamental reason for abandoning a project is that the resources used could be better employed elsewhere, i.e., the opportunity cost is too high. The other options are either less fundamental or not directly relevant.

Step-by-Step Reasoning

  1. Option A: "The construction cost is greater than the running cost." This compares two types of costs for the same project. Even if construction cost exceeds running cost, that does not necessarily mean the project should be abandoned; it might still be worthwhile if the benefits exceed total costs. So this is not the most likely reason.

  2. Option B: "The external cost is greater than the external benefit." Externalities are important, but the question is about abandoning the project entirely. Even if external costs exceed external benefits, the project might still have private benefits that outweigh total costs. Moreover, external costs and benefits are part of a cost-benefit analysis, but the most fundamental reason is still opportunity cost.

  3. Option C: "The future costs are difficult to calculate." Difficulty in calculation is a practical problem, not an economic reason for abandonment. It might lead to uncertainty, but it is not the most likely reason.

  4. Option D: "The opportunity cost is too high." This is the correct answer. Opportunity cost is the value of the next best alternative forgone. If the resources used for the rail link could produce greater benefits in other uses (e.g., improving existing transport, healthcare, education), then the project should be abandoned. This is the most fundamental economic reason.

Key Takeaways

  • Opportunity cost is the most important concept in decision-making under scarcity.
  • When evaluating a project, the relevant cost is not just the monetary cost but the value of the best alternative forgone.
  • Other cost concepts (construction cost, external cost) are secondary to opportunity cost.

Common Mistakes

  • Confusing opportunity cost with monetary cost or external cost.
  • Thinking that difficulty in calculating future costs is a reason to abandon a project; it is a practical issue but not an economic one.
  • Not recognising that opportunity cost applies to all levels of decision-making, including government projects.

Things to Be Careful About

  • Opportunity cost is not the sum of all alternatives, but the value of the single next best alternative.
  • The question asks for the "most likely reason", so we need to identify the most fundamental economic reason.
  • In multiple-choice questions, eliminate options that are less plausible based on economic principles.
Techniques used
apply the concept of opportunity cost to a government decisiondistinguish opportunity cost from other cost concepts

The rest of this paper

29 more questions
  • Q2Economic Systems · Scarcity, Choice and Opportunity Cost1M
  • Q3Production Possibility Curves1M
  • Q4Factors of Production · International Trade and Comparative Advantage1M
  • Q5Demand and Supply1M
  • Q6Demand and Supply1M
  • Q7Elasticities of Demand1M
  • Q8Elasticities of Demand1M
  • Q9Methods of Government Intervention in Markets1M
  • Q10Price Elasticity of Supply1M
  • Q11Demand and Supply · Market Equilibrium and the Price Mechanism1M
  • Q12Demand and Supply1M
  • Q13Consumer and Producer Surplus1M
  • Q14(Legacy) - Externalities and Cost-Benefit Analysis1M
  • Q15(Legacy) - Externalities and Cost-Benefit Analysis1M
  • Q16(Legacy) - Externalities and Cost-Benefit Analysis1M
  • Q17Classification of Goods and Services1M
  • Q18Methods of Government Intervention in Markets1M
  • Q19International Trade and Comparative Advantage1M
  • Q20Protectionism1M
  • Q21(Legacy) - Economic Integration1M
  • Q22Balance of Payments1M
  • Q23Factors of Production1M
  • Q24Price Stability1M
  • Q25Price Stability1M
  • Q26Balance of Payments1M
  • Q27Exchange Rates1M
  • Q28Elasticities of Demand1M
  • Q29Exchange Rates1M
  • Q30Exchange Rates · Monetary Policy1M
Loading the full paper…